Permit Process in Woodside

  • Review: ADUs and JADUs are ministerial, with no discretionary review or hearing. The Planning Director approves or denies within 60 days of a complete application. For an ADU proposed with a new main dwelling, the Director need not act before the main dwelling permit is issued.
  • Denial: Requires a finding that the ADU would be detrimental to public health and safety, with written reasons within 60 days. The Town cannot deny an ADU over nonconforming conditions, code violations, or unpermitted structures that pose no health or safety threat and would not be affected by the ADU. Approval cannot be conditioned on correcting nonconforming zoning conditions.
  • Notice: Projects using a setback exception or the 800 sf exception require notice to adjacent owners, including across an abutting road, within 5 business days of a complete application. The notice states there are no appeal rights.
  • Permit routing: Stand alone proposed JADUs, and/or ADUs are reviewed by all Town departments with submitted construction permit applications (building/site development). General construction applications require review by the Town of Woodside, Woodside Fire Protection District, and San Mateo County Environmental Health. Must obtain a sewer permit from the West Bay Sanitary District before starting construction (www.westbaysanitary.org or call 650-321-0384).

Where ADUs Are Allowed in Woodside

Attached ADUs: R-1, SR, RR, SCP-5/7.5/10; in CC, within a building only.

Detached ADUs: R-1, SR, RR, SCP-5/7.5/10.

How Many Units & Lot Rules in Woodside

  • Guaranteed unit: One 800 sf ADU may be built even if other zoning rules would prevent it, once infeasibility is shown (see Exceptions).
  • Floor area: The first 800 sf of one ADU, or 800 sf combined across two ADUs, does not count toward maximum main residence size or Total Floor Area (TFA). Area above that counts toward TFA.
  • Lots under 1 acre: One ADU, attached or detached, plus one JADU.
  • Lots 1 acre or more: Up to four units total: no more than three ADUs, attached or detached; a fourth unit is allowed only if at least one of the four is a JADU.
  • Barn ADUs and JADUs count toward these limits.

Size Limits in Woodside

  • Min: Minimum allowed by Building Code.
  • Max attached ADU: 50% of the main residence size, including the ADU, or 1,500 sf, whichever is less.
  • Max detached ADU: 1,500 sf, including any attached garage.
  • Within basic setbacks: No more than 800 sf of an ADU’s floor area.
  • ADU within a barn: Up to 50% of the barn footprint, but never limited below 850 sf, or 1,000 sf with more than one bedroom.
  • Barn or stable conversion: One existing barn or stable per lot may exceed 1,500 sf if the §153.211(B)(1) standards are met.
  • Basement ADU: Same size limits as attached and detached ADUs.
  • Max JADU: 500 sf

Height in Woodside

  • Attached, meeting basic setbacks: Up to the height allowed for a two-story main residence (28 ft in R-1; 30 ft in SR, RR, SCP).
  • Attached, within basic setbacks: 17 ft, with 11 ft plate height.
  • Detached: 17 ft, with 11 ft plate height.
  • Above a detached garage, meeting basic setbacks: 18 ft, with 12 ft plate height.
  • Greater heights: see Exceptions.

Setbacks in Woodside

  • Basic setbacks (Table H; front / rear / side, under 17 ft tall):R-1: 30 ft / 25 ft / 15 ft. SR: 50 / 25 / 20 ft.RR and SCP: 50 ft / 50 ft / 50 ft.Taller structures, Woodside Glens lots, and Woodside Hills differ; check Table H.
  • New detached ADU: 4 ft side and rear; front per Table H.
  • New attached ADU: 4 ft side and rear, but no part of the main residence may be in the required setbacks.
  • Limit in basic setbacks: Any size ADU may use the 4 ft setback, but only 800 sf of its floor area may be within basic setbacks.
  • Multiple ADUs: Only one unit may use the 4 ft setback. Other new units must meet basic setbacks, unless created by converting space in an existing structure.
  • Conversions: No new setback for an existing garage or accessory structure.
  • Above an existing garage: 4 ft or the garage’s existing setback, whichever is greater.
  • Front setback: May be reduced only through the Exceptions row process for one 800 sf ADU.

Parking in Woodside

  • JADUs: No parking required.
  • ADUs: One space per ADU with one or more bedrooms; none for studios. Tandem parking and parking in setback areas are allowed unless specific findings show they are not feasible.
  • No parking required if the ADU: Is within ½ mile walking distance of public transit, including stations and bus stops; is in an architecturally and historically significant historic district; is part of the existing main residence or an existing accessory structure; is in an area where parking permits are required but not offered to the occupant; is within one block of a car-share vehicle; or is proposed with a new dwelling on the same lot and meets one of these criteria.

Owner Occupancy in Woodside

JADUs: Required; the owner may live in the main residence or the JADU. Not required if the owner is a governmental agency, land trust, or housing organization.

ADUs: Not required.

Other Requirements, Design & Rentals in Woodside

  • Portions over 800 sf: Any portion of an ADU over 800 sf must meet all development standards for the zoning district and may not encroach into basic setbacks.
  • Fire and building: ADU shall comply with Fire District and Building Department regulations. Contact Woodside Fire Protection District and Woodside Building Department. Sprinklers are not required unless required for the main residence, and an ADU does not trigger them in an existing residence. Barn ADUs and the barn require sprinklers and firewall separation.
  • Septic: Limitations to septic installation may apply. Contact Town of Woodside and San Mateo County Department of Environmental Health. An ADU may use a dedicated system or one shared with the main residence or other ADUs.
  • Utilities: ADU shall have all utility connects prescribed by CBC/CRC.
  • Driveway: Use the principal access driveway unless a second driveway exception is approved under §151.44.
  • Rentals: No terms under 30 consecutive days.
  • Barn conversions: Location, footprint, heights, and eaves may not change; exterior materials are restricted; the unit may later convert only to a barn or stable; a covenant must be recorded.
  • Historic structures: Conversion of existing historical structures into ADUs is encouraged by the Town if the project complies with all applicable Zoning and Building Codes, and the California Secretary of Interior Standards for Historical Resources.

Fees & Real Permit Examples in Woodside

ADU – 1,493 sf, detached: $20,700*No Town building permit/inspection fees are required

State-Law Protections & Exceptions in Woodside

  • 800 sf ADU: If one 800 sf ADU cannot meet all zoning rules, the applicant submits the information the Town requests, such as a survey or septic study, showing infeasibility. The Planning Director then decides which rules to reduce or waive, choosing locations with the fewest impacts on sensitive areas.
  • Height, detached: One ADU of 800 sf or less, 16 ft or lower, has no plate height limit if it complies with Gov. Code §66323. 18 ft with a multistory multifamily primary structure. 18 ft, or 20 ft to match the main residence roof pitch, within ½ mile walking distance of a major transit stop or high-quality transit corridor.
  • Downward-sloped lots: Up to 28 ft on the downslope side, with limits on the upslope side, if average slope is 15% or more, basic setbacks are met, and the footprint is 1,500 sf or less.
  • Shed roofs: Plate height up to 14 ft on the taller side and 11 ft on the shorter side, if basic setbacks are met.
  • Above a detached garage: Up to 24 ft with 18 ft plate height if the lot meets the minimum subdivision size and added setbacks are provided: 2 ft for each foot over 12 ft plate or 18 ft height, from R-1: 30/25/22.5 ft; SR: 50/30/30 ft; RR and SCP: 50/50/50 ft (front/rear/side).
  • Dormers: Above a detached garage meeting basic setbacks, up to 65% of each roof side.
  • Slopes: An ADU, its septic system, or utilities may be on 35%–50% slopes if infeasible on slopes of 35% or less. The ADU may not include an attached garage, new main residence area, or other non-ADU use.

Official Woodside ADU Resources

Let's plan your Woodside ADU

Tell us about your lot and goals. We will show you what you can build in Woodside, what it costs and how long it takes.

Book a free consultationCall (650) 770-3586

More from iBuilders

Everything ADU, the complete Bay Area ADU guide · Garage to ADU conversions · Room additions · Full house remodeling

ADU Rules in Other Bay Area Cities

Rules, fees and processes change. This page summarizes Woodside's published ADU rules for planning purposes; confirm details with the city before you build. Not legal advice. iBuilders Design and Build · CSLB #1077269 · 710 Lakeway Dr, Suite 200, Sunnyvale, CA 94085.